Contents
1.1
Purpose of
the Report
1.2
Structure
of the Report
2.1
Background
2.2
General
Site Description
2.3
Major
Activities Undertaken
2.4
Project
Organisation and Management Structure
2.5
Status of
Environmental Approval Documents
3
Environmental Monitoring and Audit Requirements
3.1
Environmental
Monitoring
3.1.1
Air Quality
3.1.2
Odour
3.2
Site Audit
3.2.1
Water Quality
3.2.2
Landscape and Visual
4.1
Air Quality
4.1.1
Operation Phase Monitoring
4.2
Odour
4.2.1
Operation Phase Monitoring
4.3
Water
Quality
4.3.1
Operation Phase Monitoring
4.4
Waste
Management
4.4.1
Operation Phase Monitoring
5.1
Environmental
Site Audit
5.1.1
Operation Phase
5.2
Landscape
and Visual Audit
6
Environmental Non-conformance
6.1
Summary of
Environmental Non-Compliance
6.2
Summary of
Environmental Complaint
6.3
Summary of
Environmental Summon and Successful Prosecution
7.1
Key Issues
for the Coming Reporting Period
LIST OF TABLES
Table 2.1 Summary of Activities Undertaken in the
Reporting Period
Table 2.2 Summary of Environmental Licensing,
Notification and Permit Status
Table 3.1 Sampling and
Laboratory Analysis Methodology
Table 3.2 Emission Limit
for CAPCS Stack
Table 3.3 Emission Limit
for CHP Stack
Table 3.4 Emission Limit
for ASP Stack
Table 3.5 Emission Limit
for Standby Flaring Gas Unit ()
Table 3.6 Odour Intensity
Level
Table 3.7 Action and
Limit Levels for Odour Nuisance
Table 3.8 Event and Action Plan for Odour Monitoring
Table 3.9 Discharge Limits for Effluent (as stipulated
in WT00024352-2016)
Table 4.1 Hourly Average of Parameters Recorded for
CAPCS
Table 4.2 Hourly Average of Parameters Recorded for
CHP 1
Table 4.3 Hourly Average of Parameters Recorded for
CHP 2
Table 4.4 Hourly Average of Parameters Recorded for
CHP 3
Table 4.5 Hourly Average of Parameters Recorded for ASP
Table 4.6 Results of the Discharge Sample Collected on
10 June 2021
Table 4.7 Results of the Discharge Sample Collected on
8 July 2021
Table 4.8 Results of the Discharge Sample Collected on
11 and 30 August 2021
Table 4.9 Results of the Discharge Sample from the
Petrol Interceptor 1 on 11 August 2021
Table 4.10 Results of the Discharge
Sample from the Petrol Interceptor 2 on 11 August 2021
Table 4.11
Quantities of Waste Generated from the Operation of the Project
LIST OF ANNEXES
Annex E Environmental complaint, Environmental
Summons and Prosecution Log |
The construction works of No.
EP/SP/61/10 Organic Resources Recovery Centre Phase 1 (the
Project) commenced on 21 May
2015. This is the 25th quarterly Environmental Monitoring and
Audit (EM&A) report presenting the EM&A works carried out during the
period from 1 June 2021 to 31 August 2021 in accordance with the EM&A
Manual. Substantial completion of the construction works was confirmed on
3 December 2018. In the meantime, the operation phase EM&A programme
had commenced in March 2019. Substantial Completion in respect of
substantial part of the Works was confirmed on 24 February 2020. The
construction phase EM&A programme was completed in the end of February
2020.
Summary of Works
undertaken during the Reporting Month
Works undertaken in the reporting
month included:
·
Operation of the Project, including organic waste
reception, and operation of the pre-treatment facilities, anaerobic digesters, composting
facilities, air pollution control systems, on-line emission monitoring system
for the Centralised Air Pollution Control Unit (CAPCS), Co-generation Units
(CHP)s and Ammonia Stripping Plant (ASP), and the wastewater treatment plant;
and
·
Process fine-tune, including adjustment of the ASP
with new treatment media, modification of Continuous Environmental Monitoring
System (CEMS) and Supervisory Control and Data Acquisition System (SCADA)
rectification and improvement works following equipment failures and the
alteration of different operation modes and measures to adapt to the high
variation of SSOW nature and sources.
Environmental
Monitoring and Audit Progress
Air Quality
Monitoring
Exceedances on NOx, SO2, VOC and HF from CHP
and CO, NOx and NH3 from
ASP were recorded on the on-line monitoring system in June 2021.
Exceedances on NOx,
SO2 and VOCs from CHP and CO, NOx, SO2, VOCs, NH3, HCl and HF from ASP were
recorded on the on-line monitoring system in July 2021. Exceedances
on NOx and SO2 from CHP and NOx, SO2, VOCs and
NH3 from ASP were recorded on the on-line monitoring system in
August 2021. It should be noted that measurements recorded under abnormal
operating conditions, e.g. start up and stopping of stacks, unstable operation,
test runs and interference of sensor, are disregarded.
In June 2021, exceedances in emission parameters of CHP were found to be
a result of low biogas loading and unstable performance at CHP. The
exceedances of ASP were found to be a result of incomplete combustion of biogas
at ASP in June. In July, exceedances
in emission parameters of CHP were found to be a result of low biogas loading
and hence led to unstable performance at CHP. The exceedances of ASP were
found to be a result of unstable conditions in the column and the thermal oxidiser of the ASP. In August,
the exceedances in NOx of CHP were found to be a result of the low biogas
loading at the CHPs and the unstable condition of CHP1. The exceedances
of SO2 of CHPs and the ASP were found to be a result of the tripping
of the desulphurisation system. The exceedances of ASP were found to be
result of unstable condition at the thermal destructor of the ASP.
The Contractor has implemented
mitigation measures to control the exceedance (including arranging for the
supplier of CHP to perform on-site adjustment to improve CHP performance and
tuning the thermal combustion unit of the ASP to optimise combustion efficiency
and overall performance).
The Contractor is recommended to
closely monitor the processes of the modification of the ASP and the
post-modification monitoring of emission level to avoid any exceedance.
As similar issues have been
re-occurred for sometimes, the Contractor is advised to undertake a
comprehensive review of the operation of the concerned systems and the
effectiveness of the existing mitigation measures and proposed further measures
to avoid the exceedance.
Odour patrols were conducted by the
independent odour patrol team of ALS Technichem (HK)
Pty Ltd on 9 July and 9 August 2021. No Level 2 Odour Intensity was
recorded during odour patrols.
No
non-compliance to the effluent discharge limit stipulated in the discharge
licence issued by the EPD under the Water Pollution Control Ordinance
was recorded during this reporting period.
Waste generated from the operation
of the Project includes chemical waste, waste generated from pre-treatment
process and general refuse.
3,420 L of chemical waste was
collected by licenced waste collector from the operation of the Project.
1,658.51 tonnes of waste generated
from pre-treatment process from the operation of the Project was disposed of at
landfill. Among the recyclable waste generated from pre-treatment process
from the operation of the Project, 0.00 tonnes of metals, 0.00 tonnes of
papers/ cardboard packing and 0.00 tonnes of plastics were sent to recyclers
for recycling during the reporting period.
Around 8.88 tonnes of general
refuse from the operation of the Project was disposed of at landfill.
Among the recycled general refuse from the operation of the Project, 0.00
tonnes of metals, 0.00 tonnes of papers/ cardboard packing and 0.00 tonnes of
plastics were sent to recyclers for recycling during the reporting period.
Findings of
Environmental Site Audit
A
summary of the monitoring activities undertaken in this reporting period is
listed below:
·
Joint Environmental Site Inspections |
3
times |
·
Landscape & Visual Inspections |
3
times |
Monthly
joint environmental site inspections were carried out. The environmental
control/ mitigation measures (related to air quality, water quality, waste
(including land contamination prevention), hazard-to-life and landscape and
visual) recommended in the approved EIA Report and the EM&A Manual were
properly implemented by the Contractor during the reporting month.
Environmental
Exceedance/Non-conformance/Compliant/Summons and Prosecution
Exceedances for
the air emission limits for the CHP and ASP stacks were recorded during the
reporting period.
No complaint/ summon/prosecution
was received in this reporting period.
Future Key
Issues
Activities to be undertaken in the
next reporting month include:
·
Operation of the Project.
·
Modification of the CHP and ASP to control the air
emission.
ERM-Hong Kong, Limited (ERM) was appointed
by OSCAR Bioenergy Joint Venture (the Contractor) as the Environmental Team
(ET) to undertake the construction Environmental Monitoring and Audit
(EM&A) programme for the Contract No. EP/SP/61/10 of Organic Waste
Treatment Facilities Phase I, which the project name has been updated
to Organic Resources Recovery Centre (Phase I) (the
Project) since November 2017. ERM was also
appointed by the Contractor to undertake the operation EM&A programme
starting 1 March 2019.
This is the 25th
Quarterly EM&A report which summarises the monitoring results and audit
findings for the EM&A programme during the reporting period from 1 June
2021 to 31 August 2021.
The structure of the report is as
follows:
Section 1: Introduction
It details the
scope and structure of the report.
Section
2: Project Information
It
summarises the background and scope of the Project, site description, project
organisation and status of the Environmental Permits (EP)/licences.
Section
3: Environmental Monitoring and Audit Requirements
It summarises
the environmental monitoring requirements including monitoring parameters,
programmes, methodologies, frequency, locations, Action and Limit Levels,
Event/Action Plans, as well as environmental audit requirements as recommended
in the EM&A Manual and approved EIA report.
Section
4: Monitoring Results
It summarises monitoring
results of the reporting period.
Section
5: Site Audit
It summarises
the audit findings of the environmental as well as landscape and visual site
audits undertaken within the reporting period.
Section
6: Environmental Non-conformance
It summarises
any exceedance of environmental performance standard, environmental complaints
and summons received within the reporting period.
Section
7: Further Key Issues
It summarises
the impact forecast for the next reporting month.
Section
8: Conclusions
The Organic Resources Recovery Centre
(ORRC) Phase I development (hereinafter referred to as “the Project”) is to
design, construct and operate a biological treatment facility with a capacity
of about 200 tonnes per day and convert source-separated organic waste from
commercial and industrial sectors (mostly food waste) into compost and biogas
through proven biological treatment technologies. The location of the
Project site is shown in Annex
A.
The environmental
acceptability of the construction and operation of the Project had been
confirmed by findings of the associated Environmental Impact Assessment (EIA)
Study completed in 2009. The Director of Environmental Protection (DEP)
approved this EIA Report under the Environmental Impact Assessment Ordinance
(EIAO) (Cap. 499) in February 2010 (Register No.: AEIAR-149/2010) (hereafter referred to as the approved EIA Report).
Subsequent Report on Re-assessment on Environmental Implications and Report on
Re-assessment on Hazard to Life Implications were completed in 2013,
respectively.
An Environmental Permit
(EP) (No. EP-395/2010) was issued by
the DEP to the EPD (Project Team), the Permit Holder, on 21 June 2010 and
varied on 18 March 2013 (No. EP-395/2010/A) and 21 May 2013 (No.
EP-395/2010/B), respectively. The Design Build and Operate Contract for
the ORRC Phase 1 (Contract No. EP/SP/61/10 Organic Resources Recovery Centre
(Phase 1) (the Contract)) was awarded to SITA Waste Services Limited, ATAL
Engineering Limited and Ros-Roca, Sociedad Anonima
jointly trading as the OSCAR Bioenergy Joint Venture (OSCAR or the
Contractor). A Further EP (No. FEP-01/395/2010/B) was issued by the DEP
to the OSCAR on 16 February 2015. Variation to both EPs (Nos.
EP-395/2010/B and FEP-01/395/2010/B) were made in December 2015. The latest
EPs, Nos. EP-395/2010/C and FEP-01/395/2010/C, were issued by the DEP on 21
December 2015.
Under the requirements
of Condition 5 of the EP (No. FEP-01/395/2010/C), an Environmental Monitoring
and Audit (EM&A) programme as set out in the approved EM&A Manual
(hereinafter referred to as EM&A Manual) is required to be implemented during
the construction and operation of the Project. ERM-Hong Kong, Ltd (ERM)
has been appointed by OSCAR as the Environmental Team (ET) for the construction
phase EM&A programme and the Monitoring Team (MT) for the operation phase
EM&A programme for the implementation of the EM&A programme
in accordance with the requirements of the EP and the approved EM&A Manual.
The
construction works commenced on 21 May 2015. The operation phase of the
EM&A programme commenced on 1 March 2019 ([1]). The
construction phase EM&A programme was completed in the end of February
2020.
The Project Site is located at Siu
Ho Wan in North Lantau with an area of about 2 hectares. The layout of the
Project Site is illustrated in Annex
A. The facility received and treated an average of 93 to 154
tonnes of source separated organic waste per day during the reporting month.
A summary of the major activities
undertaken in the reporting period is shown in Table 2.1.
Table 2.1
Summary of Activities Undertaken in the Reporting Period
Activities Undertaken in the Reporting Period |
·
Systems being operated – waste reception,
pre-treatment, CAPCS extraction, the digesters, the centrifuge, the composting
tunnels, the desulphurisation, the emergency flare, the CHPs, the ASP and the
biological waste water treatment plant (about 93 – 154 t/d SSOW input); and ·
Process fine-tune – adjustment of the ASP
operational parameters with new treatment media, CEMS/SCADA modification and
improvement work following equipment failures and the alteration of different
operation modes and measures to adapt to the high variation of SSOW nature
and sources. |
The project organisation chart and
contact details are shown in Annex
B.
A summary of the valid permits,
licences, and/or notifications on environmental protection for this Project is
presented in Table 2.2.
Table
2.2
Summary of Environmental Licensing, Notification and Permit Status
Permit/
Licences/ Notification |
Reference |
Validity
Period |
Remarks |
Environmental
Permit |
FEP-01/395/2010/C |
Throughout the
Contract |
Permit granted
on 21 December 2015 |
Notification of
Construction Works under the Air Pollution Control (Construction Dust)
Regulation |
Ref No. 386715 |
Throughout the
Contract |
- |
Effluent
Discharge License |
WT00024352-2016 |
3 June 2016 –
30 June 2021 |
Approved on 3
June 2016 |
Effluent Discharge
License |
WT00038391-2021 |
7 July 2021 –
30 June 2026 |
Approved on 7
July 2021 |
Chemical Waste
Producer Registration |
WPN
5213-961-O2231-01 |
Throughout the
Contract |
Approved on 29
April 2015 |
Chemical Waste Producer Registration |
WPN 5213-961-O2231-02 |
Throughout the implementation of the Project |
Approved on 10 November 2017 |
Waste Disposal
Billing Account |
Account
number: 702310 |
Throughout the
Contract |
- |
The air quality
(including odour) monitoring to be carried out during the operation phase of
the Project are described below. Although water quality monitoring is not
required for the operation phase under the EM&A programme, there are water
quality monitoring requirement under the Water Discharge Licence of the plant
under the Water Pollution Control Ordinance (WPCO). As part of
this EM&A programme, the monitoring results will be reviewed to check the
compliance with the WPCO requirements.
According to the EM&A Manual
and EP requirements, stack monitoring are required during the operation phase
of the Project.
On-line monitoring (using
continuous environmental monitoring system (CEMS) shall be carried out for the
centralised air pollution unit (CAPCS), cogeneration units (CHP) and the
ammonia stripping plant (ASP) during the operation phase. The last calibration
was carried out on 15 June 2021.
The monitoring data is transmitted
instantaneously to EPD (Regional Office) by telemetry system.
When the on-line monitoring for
certain parameter cannot be undertaken, monitoring will be carried out using
the following methodology approved by the EPD.
Table 3.1
Sampling and Laboratory Analysis Methodology
Parameters |
Method |
Stacks to be
Monitored |
Gaseous and vaporous organic
substances (including methane) |
USEPA Method 18 |
·
CAPCS ·
CHP ·
ASP |
Particulate |
USEPA Method 5 |
·
CAPCS ·
CHP ·
ASP |
Carbon monoxide (CO) |
USEPA
Method 10 |
·
CHP ·
ASP |
Nitrogen oxides (NOx) |
USEPA Method 7E |
·
CHP ·
ASP |
Sulphur dioxide (SO2); |
USEPA Method 6 |
·
CHP ·
ASP |
Hydrogen chloride (HCl) |
USEPA Method 26A |
·
CHP ·
ASP |
Hydrogen fluoride (HF) |
USEPA Method 26A |
·
CHP ·
ASP |
Oxygen (O2); |
USEPA Method 3A |
·
CAPCS ·
CHP ·
ASP |
Velocity and Volumetric Flow |
USEPA Method 2 |
·
CAPCS ·
CHP ·
ASP |
Ammonia (NH3) |
USEPA CTM 027 |
·
ASP |
Odour (including NH3
and H2S) |
EN 13725 |
·
CAPCS |
Water vapour content (continuous measurement
of the water vapour content should not be required if the sample exhaust gas
is dried before the emissions are analysed) |
USEPA Method 4 |
·
CAPCS ·
CHP ·
ASP |
Temperature |
USEPA Method 4 |
·
CAPCS ·
CHP ·
ASP |
With reference to the EM&A Manual,
the air emission of the stacks shall meet the following emission limits as
presented in Tables 3.2 to 3.5.
Table 3.2
Emission Limit for CAPCS Stack
Parameter |
Emission Level
(mg/Nm3) (a) |
VOCs (including
methane) |
680 |
Dust (or Total Suspended Particulates (TSP)) |
6 |
Odour (including NH3 & H2S) |
220 (b) |
Notes: (a)
Hourly average concentration (b)
The odour unit is OU/Nm3 |
Table 3.3
Emission Limit for CHP Stack
Parameter |
Maximum Emission
Level (mg/Nm3) (a) (b) |
Dust (or Total Suspended
Particulates) |
15 |
Carbon Monoxide |
650 |
NOx |
300 |
SO2 |
50 |
NMVOCs (c) |
150 |
VOCs
(including methane) (d) |
1,500 |
HCl |
10 |
HF |
1 |
Notes: (a)
All values refer to an oxygen content in the exhaust gas of 6% and dry basis. (b)
Hourly average concentration (c)
NMVOCs should be monitored by gas sampling and laboratory analysis at an
agreed interval. For the first 12 months (starting from August 2019),
monitoring should be carried out at quarterly intervals. The monitoring
frequency should then be reduced to half-yearly for next 12 months (starting
from August 2020). (d)
The VOCs emission limit include methane as biogas is adopted as fuel in the
combustion process. |
Table 3.4
Emission Limit for ASP Stack
Parameter |
Maximum Emission Level
(mg/Nm3) (a) (b) |
Dust (or Total Suspended Particulates) |
5 |
Carbon Monoxide |
100 |
NOx |
200 |
SO2 |
50 |
VOCs
(including methane) (c) |
20 |
NH3 |
35 |
HCl |
10 |
HF |
1 |
Notes: (a)
All values refer to an oxygen content in the exhaust gas of 11% and dry
basis. (b)
Hourly average concentration (c)
The VOCs emission limit include methane as biogas is adopted as fuel in the
combustion process. |
Table
3.5 Emission Limit for Standby
Flaring Gas Unit ([2])
Parameter |
Maximum Emission
level (mg/Nm3) (a) (b) |
Dust (or Total Suspended
Particulates) |
5 |
Carbon Monoxide |
100 |
NOx |
200 |
SO2 |
50 |
VOCs (including methane) (c) |
20 |
HCl |
10 |
HF |
1 |
Notes: (a) All
values refer to an oxygen content in the exhaust gas of 11% and dry basis. (b)
Hourly average concentration (c)
The VOCs emission limit include methane as biogas is adopted as fuel in the
combustion process. |
To determine
the effectiveness of the proposed odour mitigation measures and to ensure that
the operation of the ORRC1 will not cause adverse odour impacts, odour
monitoring of the CAPCS stack (see Section 3.1.1) and odour patrol will
be carried out.
Odour patrol shall be conducted by
independent trained personnel/ competent persons in summer months (i.e. from
July to September) for the first two operational years of ORRC1 at monthly
intervals along an odour patrol route at the Project Site boundary as shown in Annex A.
The perceived odour intensity is
divided into 5 levels. Table 3.6 describes the odour intensity for
different levels.
Table 3.6
Odour Intensity Level
Level |
Odour Intensity |
0 |
Not detected. No odour perceived
or an odour so weak that it cannot be easily
characterised or described |
1 |
Slight identifiable odour,
and slight chance to have
odour nuisance |
2 |
Moderate identifiable
odour, and moderate chance to have odour nuisance |
3 |
Strong identifiable, likely
to have odour nuisance |
4 |
Extreme severe odour,
and unacceptable odour level |
Table 3.7 shows
the action level and limit level to be used for odour patrol. Should any
exceedance of the action and limit levels occurs, actions in accordance with
the event and action plan in Table 3.8 should be carried out.
Table 3.7
Action and Limit Levels for Odour Nuisance
Parameter |
Action Level |
Limit Level |
Odour Nuisance (from odour
patrol) |
When one documented compliant is
received (a), or Odour Intensity of 2 is measured from odour patrol. |
Two or more documented complaints
are received (a) within a week; or Odour intensity of 3 or above is measured
from odour patrol. |
Note: (a)
Once the complaint is received by the Project Proponent (EPD), the Project
Proponent would investigate and verify the complaint whether it is related to
the potential odour emission from the ORRC1 and its on-site wastewater
treatment unit. |
Table 3.8
Event and Action Plan for Odour Monitoring
Event |
Action |
|
|
Person-in-charge of Odour Monitoring |
Project Proponent (a) |
Action Level |
|
|
Exceedance of action level (Odour
Patrol) |
1. Identify source/reason of
exceedance; 2. Repeat odour patrol to confirm
finding. |
1. Carry out investigation to
identify the source/reason of exceedance. Investigation should be
completed within 2 weeks; 2. Rectify any unacceptable
practice; 3. Implement more mitigation
measures if necessary; 4. Inform Drainage Services
Department (DSD) or the operator of the Siu Ho Wan Sewage Treatment Works
(SHWSTW) if exceedance is considered to be caused by the operation of the
SHWSTW. 5. Inform North Lantau Refuse
Transfer Station (NLTS) operator if exceedance is considered to be caused by
the operation of NLTS. |
Exceedance of action level (Odour
Complaints) |
1. Identify source/reason of
exceedance; 2. Carry out odour patrol to
determinate odour intensity. |
1. Carry out investigation and
verify the complaint whether it is related to potential odour emission from
the nearby SHWSTW; 2. Carry out investigation to
identify the source/reason of exceedance. Investigation should be
completed within 2 weeks; 3. Rectify any unacceptable
practice; 4. Implement more mitigation
measures if necessary; 5. Inform DSD or the operator of
the SHWSTW if exceedance is considered to be caused by the operation of the
SHWSTW. 6. Inform NLTS operator if
exceedance is considered to be caused by the operation of NLTS. |
Limit Level |
|
|
Exceedance of limit level |
1. Identify source/reason of
exceedance; 2. Inform EPD; 3. Repeat odour patrol to
confirm findings; 4. Increase odour patrol
frequency to bi-weekly; 5. Assess effectiveness of
remedial action and keep EPD informed of the results; 6. If exceedance stops, cease
additional odour patrol. |
1. Carry out investigation to
identify the source/reason of exceedance. Investigation should be
completed within 2 week; 2. Rectify any unacceptable
practice; 3. Formulate remedial actions; 4. Ensure remedial actions
properly implemented; 5. If exceedance continues,
consider what more/enhanced mitigation measures should be implemented; 6. Inform DSD or the operator of
the SHWSTW if exceedance is considered to be caused by the operation of the
SHWSTW. |
Note: (a)
Project Proponent shall identify an implementation agent. |
Environmental mitigation measures
(related to air quality, water quality, waste, land contamination,
hazard-to-life, and landscape and visual) to be implemented during the
operation phase of the Project are recommended in the approved EIA Report and
EM&A Manual and are summarised in Annex C. Monthly site audits for operation phase
will be carried out to check the implementation of these measures.
Compliance audits are to be
undertaken to ensure that a valid discharge licence has been issued by EPD
prior to the discharge of effluent from the operation of the Project
site. Under Effluent Discharge Licence WT00024352-2016 (expired in June
2021), the audit shall be conducted to ensure that the effluent quality is in
compliance with the discharge licence requirements. The effluent quality
shall meet the discharge limits as described in Table 3.9.
Under Effluent Discharge Licence WT00038391-2021 (effective from
July 2021), the effluent quality shall meet the discharge limits as described
in Table 3.10 and Table 3.11.
Table 3.9 Discharge
Limits for Effluent (as stipulated in WT00024352-2016)
Parameters |
Discharge Limit
(mg/L) |
Flow Rate (m3/day) |
685 |
pH (pH units) |
6-10 (a) |
Suspended Solids |
800 |
Biochemical Oxygen Demand (5
days, 20°) |
800 |
Chemical Oxygen Demand |
2,000 |
Oil & Grease |
40 |
Total Nitrogen |
200 |
Total Phosphorus |
50 |
Surfactants (total) |
25 |
Note: (a)
Range. |
Table 3.10
Discharge Limits for Effluent from the Effluent Storage Tank (as
stipulated in WT00038391-2021)
Parameters |
Discharge Limit
(mg/L) |
Flow Rate (m3/day)
(a) |
645 |
pH (pH units) (b) |
6-10 (c) |
Suspended Solids (b) |
800 |
Biochemical Oxygen Demand (5
days, 20°) (b) |
800 |
Chemical Oxygen Demand (b) |
2,000 |
Oil & Grease (b) |
40 |
Total Nitrogen (b) |
200 |
Total Phosphorus (b) |
50 |
Surfactants (total) (b) |
25 |
Notes: (b) Flow
rate is not a parameter required to be monitored and reported by the
Contractor in accordance to Section B2 of the Effluent Discharge Licence
under the WPCO. (c)
Parameters required to be monitored and reported by the Contractor in accordance
to Section B2 of the Effluent Discharge Licence under the WPCO. (d)
Range. |
Table 3.11
Discharge Limits for Effluent from the Petrol Interceptor(s) (as
stipulated in WT00038391-2021)
Parameters |
Discharge Limit
(mg/L) |
Flow Rate (m3/day)
|
245 (a) |
Suspended Solids (b) |
30 |
Chemical Oxygen Demand (c) |
80 |
Oil & Grease (c) |
20 |
Surfactants (total) (b) |
15 |
Notes: (a) The
surface runoff flow rate limit was estimated by the overall yearly rainfall
data. As the actual flowrate from the petrol interceptors depends on
the weather condition instead of the performance of the petrol interceptor,
monitoring and reporting of this parameter is not required. Hence this
parameter is not reported in Error! Reference source not found.
and Table 4.10. (b)
Parameter not required to be reported in accordance to Section B2 of the
Effluent Discharge Licence under the WPCO. (c)
Parameters required to be reported in accordance to Section B2 of the
Effluent Discharge Licence under the WPCO. |
In accordance with EM&A Manual,
the landscape and visual mitigation measures shall be implemented.
For operation phase, site
inspection shall be conducted once a month for the first year of operation of
the Project. All measures as stated in the implementation schedule of the
EM&A Manual (see Annex C),
including compensatory planting, undertaken by both the Contractor and the
specialist Landscape Sub-Contractor during the first year of the operation
phase shall be audited by a Registered Landscape Architect (RLA) to ensure
compliance with the intended aims of the measures and the effectiveness of the
mitigation measures.
The concentrations of concerned air
pollutants emitted from the stacks of the CAPCS, CHP, and ASP during the
reporting period are monitored on-line by the continuous environmental
monitoring system (CEMS). During the reporting period, there is no need
to operate the standby flare and therefore no monitoring of the flare stack was
undertaken.
With reference to the emission
limits shown in Tables 3.2, 3.3 and 3.4, the hourly average
concentrations and the number of exceedances of the concerned air emissions
monitored for the CAPCS, CHP and ASP during this reporting period are presented
in Tables 4.1 to 4.5.
It should be noted that
measurements recorded under abnormal operating conditions, e.g. start up and
stopping of stacks, unstable operation, test runs and interference of sensor,
are disregarded.
Table 4.1
Hourly Average of Parameters Recorded for CAPCS
Parameter |
Range of Hourly
Average Conc. (mg/Nm3) |
Emission Limit
(mg/Nm3) |
Exceedance
Identified |
Remarks |
VOCs (including
methane) |
5.15
– 16.23 |
680 |
Nil |
Nil |
Dust (or TSP) |
0.00
– 1.36 |
6 |
Nil |
Nil |
Odour (including NH3 & H2S) (b) |
0.27
– 218.09 |
220 |
Nil |
Nil |
Note: (a)
The odour unit is OU/Nm3. |
Table 4.2 Hourly
Average of Parameters Recorded for CHP 1
Parameter |
Range
of Hourly Average Conc. (mg/Nm3) (a) |
Max.
Emission Limit (mg/Nm3) |
Exceedance Identified |
Remarks |
Dust
(or TSP) |
0 – 5 |
15 |
Nil |
Nil |
Carbon
Monoxide |
0 – 513 |
650 |
Nil |
Nil |
NOx |
0 – 366 |
300 |
Identified
(d) |
System
unstable (e.g. low efficiency, unstable column temperature ) |
SO2 |
0
– 173 |
50 |
Identified (e) |
Disruption
of power supply (f). Desulpurisation system tripped and resumed to normal after urgent
maintenance (g). |
NMVOCs (b) |
Nil |
150 |
Nil |
Nil |
VOCs
(including methane) (c) |
0
– 1,103 |
1,500 |
Nil |
Nil |
HCl |
0
– 1 |
10 |
Identified |
Nil |
HF |
0
– 1 |
1 |
Nil |
Nil |
Notes: (a) All values
refer to an oxygen content in the exhaust gas of 6% and
dry basis. (b)
No sampling was undertaken at CHP 1 as biogas production rate could not sustain
the operation of the CHP stack for the scheduled sampling on 8 February 2021.
(c)
The VOCs emission limit include methane as biogas is adopted as fuel in the
combustion process. (d)
Dates with exceedances on NOx
(number of exceedances on the day) were identified on 4 (1), 10 (1), 13 (4),
14 (4), 18 (1), 19 (2), 20 (2) and 29 (2) June 2021; 1 (3),
7 (1), 9 (2), 11 (6), 12 (3) and 19 (1) July 2021; 15 (1), 16 (4) and 20 (1) August 2021 (e)
Dates with exceedances on SO2 (number of exceedances on the day)
were identified on were identified on 7 (8) and 22 (3) June 2021. (f)
On 7 June 2021. (g)
On 22 June 2021. |
Table 4.3
Hourly Average of Parameters Recorded for CHP 2
Parameter |
Range of Hourly
Average Conc. (mg/Nm3) (a) (b) |
Max. Emission Limit
(mg/Nm3) |
Exceedance Identified |
Remarks |
Dust (or TSP) |
0 – 13 |
15 |
Nil |
Nil |
Carbon Monoxide |
0 – 571 |
650 |
Nil |
Nil |
NOx |
0 – 499 |
300 |
Identified (d) |
System unstable (e.g. low
efficiency, unstable column temperature ) |
SO2 |
0 – 159 |
50 |
Identified (e) |
Disruption
of power supply (f). Desulpurisation system tripped and resumed to normal after urgent
maintenance. (g) |
NMVOCs (b) |
6.0 |
150 |
Nil |
Nil |
VOCs (including
methane) (c) |
0 – 1,284 |
1,500 |
Nil |
Nil |
HCl |
0 – 1 |
10 |
Nil |
Nil |
HF |
0 – 1 |
1 |
Nil |
Nil |
Notes: (a) All
values refer to an oxygen content in the exhaust gas of 6% and
dry basis. (b)
Bi-annual sampling of NMVOCs was conducted in CHP 2 on 8 February 2021. The
hourly average concentration for NMVOC was 6 mg/Nm3. No
exceedance was identified. The VOCs emission limit include methane as biogas
is adopted as fuel in the combustion process. The result is provided in
Annex G. (c)
The VOCs emission limit include methane as biogas is adopted as fuel in the
combustion process. (d) Date with exceedances on NOx (number of
exceedances on the day) was identified on 7 (3) and 8 (5) June 2021; 5 (1),
26 (1), 28 (1) and 31 (1) July 2021; 23 (1) and 27 (1) August 2021. (e) Date with exceedances on SO2 (number of
exceedances on the day) was identified on 7 (7) and 22 (4) June 2021; 31 (3)
July 2021; 1 (5), 27 (6), 28 (23) and 31 (14) August 2021. (f)
On 7 June 2021. (g) On 22 June 2021 and in August 2021. |
Table 4.4
Hourly Average of Parameters Recorded for CHP 3
Parameter |
Range of Hourly
Average Conc. (mg/Nm3) (a) |
Max. Emission Limit
(mg/Nm3) |
Exceedances Identified |
Remarks |
Dust (or TSP) |
0 – 11 |
15 |
Nil |
Nil |
Carbon Monoxide |
0 – 263 |
650 |
Nil |
Nil |
NOx |
0 – 479 |
300 |
Identified (d) |
System unstable (e.g. low
efficiency, unstable column temperature ) |
SO2 |
0 – 148 |
50 |
Identified (e) |
Desulpurisation system tripped and resumed to normal after urgent
maintenance (f). System unstable (e.g. low efficiency,
unstable column temperature ) (g) |
NMVOCs (b) |
Nil |
150 |
Nil |
Nil |
VOCs
(including methane) (c) |
0 – 1,695 |
1,500 |
Identified (h) |
System unstable (e.g. low
efficiency, unstable column temperature ) |
HCl |
0 – 6 |
10 |
Nil |
Nil |
HF |
0 – 2 |
1 |
Identified (i) |
System unstable (e.g. low
efficiency, unstable column temperature ) |
Notes: (a)
All values refer to an oxygen content in the exhaust gas of 6% and dry basis. (b)
No sampling was undertaken at CHP3 as biogas production rate could not
sustain the operation of the CHP stack for the scheduled sampling on 8
February 2021. (c)
The VOCs emission limit include methane as biogas is adopted as fuel in the
combustion process. (d) Dates
with exceedances on NOx (number of exceedances on the day) were
identified on 8 (7), 13 (1), 14 (13), 15 (9), 17 (3), 22 (2), 23 (5), 24
(13), 25 (1) and 30 (1) June 2021; 1 (2), 2 (1) and 7 (3) July 2021; 17 (1)
and 29 (1) August 2021. (e) Dates
with exceedances on SO2 (number of exceedances on the day) were
identified on 22 (1) June 2021; 7 (1) July 2021; 17 (1), 28 (5) and 31 (14)
August 2021. (f)
On 22 June 2021. (g) On 7
July 2021. (h) Dates
with exceedances on VOC (number of exceedances on the day) were identified on
8 (1), 13 (2), 14 (7), 15 (6), 23 (1) and 30 (2) June 2021; 7 (2) July 2021. (i)
Date with exceedances on HF (number of exceedances on the day) was identified
on 17 (1) June 2021. |
Table 4.5
Hourly Average of Parameters Recorded for ASP
Parameter |
Range
of Hourly Average Conc. (mg/Nm3) (a) |
Max. Emission Limit
(mg/Nm3) |
Exceedances Identified |
Remarks |
Dust (or TSP) |
0 – 1 |
5 |
Nil |
Nil |
Carbon Monoxide |
0 – 386 |
100 |
Identified (c) |
System unstable (e.g. low efficiency, unstable column temperature) |
NOx |
0 – 801 |
200 |
Identified (d) |
System instability due to
unstable column temperature. |
SO2 |
0 – 101 |
50 |
Identified (e) |
System instability due to
unstable column temperature. |
VOCs
(including methane) (b) |
0 – 894 |
20 |
Identified (f) |
System instability due to
unstable column temperature. |
NH3 |
0 – 369 |
35 |
Identified (g) |
System instability due to
unstable column temperature. |
HCl |
0 – 17 |
10 |
Identified (h) |
System instability due to
unstable column temperature. |
HF |
0 – 2 |
1 |
Identified (i) |
System instability due to
unstable column temperature. |
Notes: (a) All
values refer to an oxygen content in the exhaust gas of 11% and dry basis. (b) The
VOCs emission limit include methane as biogas is adopted as fuel in the
combustion process. (c)
Date with exceedances on CO (number of exceedances on the day) was identified
on 6 (1) June 2021; 20 (1), 21 (1), 27 (2) and 28 (1) July 2021. (d) Dates
with exceedances on NOx (number of exceedances on the day) were identified on
6 (1), 8 (1), 14 (1) and 17 (1) June 2021; 1 (1), 6 (3), 7 (5), 10 (3), 11
(2), 12 (11), 13 (1), 16 (1), 17 (5), 19 (5), 20 (12), 21 (2), 22 (1), 23
(6), 24
(11), 25 (1), 26 (5), 27 (1), 28 (12), 29 (17), 30 (22) and 31 (10) July
2021; 1 (15), 2 (7), 5 (1),
6 (3), 7 (7), 8 (3), 11 (5), 12 (5), 13 (21), 14 (6), 16 (9), 17 (10), 18
(4), 19 (2), 20 (1), 21 (2), 22 (1), 23 (2), 24 (2), 25 (1), 27 (2), 28 (3)
and 29 (4) August 2021. (e) Dates
with exceedances on SO2 (number of exceedances on the day) were identified on
12 (1) and 27 (1) July 2021; 1
(5) August 2021. (f)
Dates
with exceedances on VOCs (number of exceedances on the day) were identified
on 12 (2), 20 (1), 27 (2), 28 (1) and 29 (3) July 2021; 1 (2) August 2021. (g) Dates
with exceedances on NH3 (number of exceedances on the day) was
identified on 6 (5), 7 (8), 8 (2), 9 (9), 10 (5), 11 (5), 12 (4), 13 (15), 14
(15), 15 (9), 16 (15), 17 (7), 18 (14), 19 (10), 23 (1), 28 (1) and 29 (4)
June 2021; 2 (3), 7 (1), 8 (1), 9 (2), 10 (4), 11 (1), 12
(12), 13 (11), 14 (12), 15 (2), 16 (2), 17 (15), 18 (7), 20 (4), 21 (13), 22
(11), 23 (3), 24 (4), 25 (5), 26 (4), 27 (3), 28 (1) and 29 (4) July 2021; 1 (1), 9 (1), 20 (3), 25 (5), 26 (4), 27 (2) and 28
(2) August 2021. (h) Dates
with exceedances on HCl (number of exceedances on the day) were identified on
27 (1) and 31 (1) July 2021. (i)
Date
with exceedances on HF (number of exceedances on the day) was identified on
12 (1) July 2021. |
Odour patrol was conducted by the
independent odour patrol team of ALS Technichem (HK)
Pty Ltd on 9 July and 9 August 2021. According to the EM&A Manual and
EP requirements, it is considered an exceedance if the odour intensity recorded
by the panellists is Level 2 or above. During this reporting period, no
Level 2 Odour Intensity was recorded. The odour patrol result is shown in
Annex H.
Effluent discharge was sampled
monthly from the Effluent Storage Tank as stipulated in the operation phase
discharge licence. Discharge from the Petrol Interceptors were sampled
bi-monthly since July 2021 as stipulated in the operation phase discharge
licence. The results of the discharge samples from the Effluent Storage
Tank are recorded in Table 4.6 to 4.8. The results of the
discharge samples from the Petrol Interceptors are recorded in Table 4.9 and
4.10.
Table 4.6
Results of the Discharge Sample Collected from the Effluent Storage Tank on 10
June 2021
Parameters |
Discharged Effluent
Concentration (mg/L) |
Discharge Limit
(mg/L) |
Compliance with
Discharge Limit |
pH (pH units) |
7.94 - 8.36 |
6-10 (a) |
Yes |
Suspended Solids |
237 |
800 |
Yes |
Biochemical Oxygen Demand (5
days, 20°) |
48 |
800 |
Yes |
Chemical Oxygen Demand |
1,340 |
2,000 |
Yes |
Oil & Grease |
<5 |
40 |
Yes |
Total Nitrogen |
102 |
200 |
Yes |
Total Phosphorus |
40.6 |
50 |
Yes |
Surfactants (total) |
<1.0 |
25 |
Yes |
Notes: (a) Daily
Average. |
Table 4.7
Results of the Discharge Sample Collected from the Effluent Storage Tank on 8
July 2021
Parameters |
Discharged Effluent
Concentration (mg/L) |
Discharge Limit
(mg/L) |
Compliance with
Discharge Limit |
pH (pH units) |
7.67
– 8.33 |
6-10 (a) |
Yes |
Suspended Solids |
217 |
800 |
Yes |
Biochemical Oxygen Demand (5
days, 20°) |
30 |
800 |
Yes |
Chemical Oxygen Demand |
1,340 |
2,000 |
Yes |
Oil & Grease |
<5 |
40 |
Yes |
Total Nitrogen |
90.4 |
200 |
Yes |
Total Phosphorus |
48.3 |
50 |
Yes |
Surfactants (total) |
<1.5 |
25 |
Yes |
Notes: (a)
Daily Average. |
Table 4.8
Results of the Discharge Sample Collected from the Effluent Storage Tank on 11
and 30 August 2021
Parameters |
Discharged Effluent Concentration
(mg/L) |
Discharge Limit
(mg/L) |
Compliance with
Discharge Limit |
pH (pH units) |
7.49 – 8.40 |
6-10 (a) |
Yes |
Suspended Solids (b) |
628 |
800 |
Yes |
Biochemical Oxygen Demand (5
days, 20°) (b) |
82 |
800 |
Yes |
Chemical Oxygen Demand (b)
|
1,830 |
2,000 |
Yes |
Oil & Grease (b) |
<5 |
40 |
Yes |
Total Nitrogen (b) |
146 |
200 |
Yes |
Total Phosphorus (c) |
46.8 |
50 |
Yes |
Surfactants (total) (b) |
2.5 |
25 |
Yes |
Notes: (a)
Daily Average. (b)
Effluent sample collected on 11 August 2021. (c)
Effluent sample collected on 30 August 2021. A joint sampling with the
EPD was carried out on 11 August 2021. While the monitoring result of
the sample collected by the EPD shown no exceedance, exceedance was found in
the sample collected by the Contractor. The Contractor has investigated
the operating conditions of the on-site wastewater treatment plant afterwards
and found no major abnormality. Therefore, additional sampling was
carried out by the Contractor on 30 August 2021, here shows the updated
result. |
Table 4.9
Results of the Discharge Sample from the Petrol Interceptor 1 on 11
August 2021
Parameters |
Discharged
Effluent Concentration (mg/L) |
Discharge
Limit (mg/L) |
Compliance
with Discharge Limit |
Suspended
Solids (b) |
5 (a) |
30 |
Yes |
Chemical
Oxygen Demand (c) |
15 (a) |
80 |
Yes |
Oil
& Grease (c) |
<5
(a) |
20 |
Yes |
Surfactants
(total) (b) |
<1.0
(a) |
15 |
Yes |
Notes: (a)
Effluent sample collected on 11 August 2021. (b)
Parameter not required to be reported in accordance to Section B2 of the
Effluent Discharge Licence under the WPCO. (c)
Parameters required to be reported in accordance to Section B2 of the
Effluent Discharge Licence under the WPCO. |
Table
4.10 Results of
the Discharge Sample from the Petrol Interceptor 2 on 11 August 2021
Parameters |
Discharged
Effluent Concentration (mg/L) |
Discharge
Limit (mg/L) |
Compliance
with Discharge Limit |
Suspended
Solids (b) |
5 (a) |
30 |
Yes |
Chemical
Oxygen Demand (c) |
32 (a) |
80 |
Yes |
Oil
& Grease (c) |
<5
(a) |
20 |
Yes |
Surfactants
(total) (b) |
<1.0
(a) |
15 |
Yes |
Notes: (a)
Effluent sample collected on 11 August 2021. (b)
Parameter not required to be reported in accordance to Section B2 of the
Effluent Discharge Licence under the WPCO. (c)
Parameters required to be reported in accordance to Section B2 of the
Effluent Discharge Licence under the WPCO. |
No exceedance of discharge limit
was recorded during the reporting period.
Wastes generated from the operation
of the Project include chemical waste, wastes generated from pre-treatment
process and general refuse ([3]).
Reference has been made to the Monthly Summary Waste Flow Table prepared by the
Contractor (see Annex D).
With reference to the relevant handling records and trip tickets of this
Project, the quantities of different types of waste generated from the
operation of the Project in the reporting month are summarised in Table 4.11.
Table 4.11
Quantities of Waste Generated from the Operation of the Project
Month / Year |
Chemical Waste |
Waste Generated from |
General Refuse |
||
|
Disposal of at CWTC |
Disposed of at Landfill (a) |
Recycled (b) |
Disposed of at Landfill (a) (d) |
Recycled (c) |
June 2021 |
0 L |
558.72 tonnes |
0.00 tonnes |
2.88 tonnes (d) |
0.00 tonne |
July 2021 |
0 L |
382.74 tonnes |
0.00 tonnes |
3.00 tonnes (d) |
0.00 tonne |
August 2021 |
3,420 L (e) |
687.05 tonnes |
0.00 tonnes |
3.00 tonnes (d) |
0.00 tonne |
Notes: (a)
Waste generated from pre-treatment process and general refuse other than
chemical waste and recyclables were disposed of at NENT landfill by
sub-contractors. (b)
Among waste generated from pre-treatment process, 0.00 tonne of metals, 0.00
tonne of papers/ cardboard packing and 0.00 tonne of plastics were sent to
recyclers for recycling during the reporting period. (c)
Among general refuse, 0.00 tonnes of metals, 0.00 tonnes of papers/ cardboard
packing and 0 tonnes of plastics were sent to recyclers for recycling during
the reporting period. (d)
It was assumed that four 240-litre bins filled with 80% of general refuse
were collected at each collection. The general refuse density was
assumed to be around 0.15 kg/L. (e)
It includes 1,200 L of spent lube oil, 2,000 L of sodium hydroxide solution
and 220 kg (regarded as 220 L) of spent absorbents contaminated with acids. |
The
monthly inspections of the operation phase of the Project covered the operation
phase environmental site inspections. The inspections checked the
implementation of the recommended mitigation measures for air quality,
landscape and visual, water quality, waste (land contamination) and
hazard-to-life stated in the Implementation Schedule (see Annex C).
Follow-up
actions resulting from the site inspections were generally taken as reported by
the Contractor. The Contractor has implemented environmental mitigation measures
recommended in the approved EIA Report and EM&A Manual.
June
2021
The
monthly inspection of the operation phase of the Project on 18 June 2021
covered the operation phase environmental site audit. Joint site
inspections was conducted by representatives of the Contractor, IEC and the MT
on 18 June 2021 as required for the operation of the Project.
July
2021
The
monthly inspection of the operation phase of the Project on 30 July 2021
covered the operation phase environmental site audit. Joint site
inspections was conducted by representatives of the Contractor, IEC and the MT
on 30 July 2021 as required for the operation of the Project.
August
2021
The
monthly inspection of the operation phase of the Project on 3 August 2021
covered the operation phase environmental site audit. Joint site
inspections was conducted by representatives of the Contractor, IEC and the MT
on 3 August 2021 as required for the operation of the Project.
It was confirmed that the necessary
landscape and visual mitigation measures during the operation phase as
summarised in Annex C
were generally implemented by the Contractor. No non-compliance in
relation to the landscape and visual mitigation measures was identified during
the site audits in this reporting period and therefore no further actions are
required. The ET/MT will keep track of the EM&A programme to check
compliance with environmental requirements and the proper implementation of all
necessary mitigation measures.
June 2021
Monthly inspection of the landscape and visual mitigation measures for
the operation phase of the Project was performed on 18 June 2021.
July 2021
Monthly inspection of the landscape and visual mitigation measures for
the operation phase of the Project was performed on 30 July 2021.
August 2021
Monthly inspection of the landscape and visual mitigation measures for
the operation phase of the Project was performed on 3 August 2021.
June 2021
Non-compliance of emission limits for
CHP and ASP were recorded during the reporting period.
The Contractor has reviewed the
organic waste treatment processes (i.e. waste reception, waste pre-treatment,
anaerobic digesters, and composting processes) and found that they were
operated normally during the reporting period. The Contractor has investigated
air pollution control systems for the CHP and ASP and identified several
potential causes for the exceedance. Remedial and follow-up actions had
been recommended to the Contractor to perform accordingly. The
Investigation Report is shown in Annex F.
July 2021
Non-compliance of emission limits for
CHP and ASP were recorded during the reporting period.
The Contractor has reviewed the
organic waste treatment processes (i.e. waste reception, waste pre-treatment,
anaerobic digesters, and composting processes) and found that they were
operated normally during the reporting period. The Contractor has investigated
air pollution control systems for the CHP and ASP and identified several
potential causes for the exceedance. Remedial and follow-up actions had
been recommended to the Contractor to perform accordingly. The
Investigation Report is shown in Annex F.
August 2021
Non-compliance of emission limits
for CHP and ASP were recorded during the reporting period.
The Contractor has reviewed the
organic waste treatment processes (i.e. waste reception, waste pre-treatment,
anaerobic digesters, and composting processes) and found that they were
operated normally during the reporting period. The Contractor has investigated
air pollution control systems for the CHP and the ASP and identified several
potential causes for the exceedance. Remedial and follow-up actions had
been recommended to the Contractor to perform accordingly. The
Investigation Report is shown in Annex F.
Activities to be undertaken for the
coming reporting period are:
·
Operation of the Project.
·
Modification of the CHP and ASP to control the air
emission.
This EM&A Report presents the
EM&A programme undertaken during the reporting period from 1 June 2021
to 31 August 2021 in accordance with EM&A Manual (Version F) and
requirements of EP (FEP-01/395/2010/C).
For the operation phase,
exceedances of the emission limits for stack monitoring (including CAPCS, CHP
and ASP stacks) were recorded under normal operating conditions during the
reporting period (see Table 8.1).
Table
8.1 Exceedances for Stack
Emissions
Stack |
Exceedances During
the Reporting Period |
Centralised Air Pollution
Control Unit (CAPCS) |
· Nil |
Cogeneration Unit (CHP) |
· Exceeded emission limit of NOx on 4, 7, 8,
10, 13, 14, 15, 17, 18, 19, 20, 22, 23, 24, 25, 29 and 30 June 2021; 1,
2, 5, 7, 9, 11, 12, 19, 26, 28 and 31 July 2021; 15, 16, 17, 20, 23, 27 and 29 August 2021. · Exceeded emission limit of SO2 on 7 and
22 June 2021; 7 and 31 July 2021; 1, 17, 27, 28 and 31 August 2021. · Exceeded emission limit of VOCs on 8, 13, 14, 15, 23
and 30 June 2021; 7 July 2021. · Exceeded emission limit of HF on 17 June 2021. |
Ammonia Stripping Plant (ASP) |
· Exceeded emission limit of CO on 6 June 2021; 20,
21, 27 and 28 July 2021. · Exceeded emission limit of NOx on 6, 8,
14 and 17 June 2021; 1, 6, 7, 10, 11, 12, 13, 16, 17, 19, 20, 21,
22, 23, 24, 25, 26, 27, 28, 29, 30 and 31 July 2021; 1, 2, 5, 6, 7, 8, 11, 12, 13, 14, 16, 17, 18, 19,
20, 21, 22, 23, 24, 25, 27, 28 and 29 August 2021. · Exceeded
emission limit of SO2 on 12 and 27 July 2021; 1 August 2021. · Exceeded
emission limit of VOCs on 12, 20, 27, 28 and 29 July 2021; 1 August 2021. · Exceeded emission limit of NH3 on 6, 7,
8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 28 and 29 June 2021; 2,
7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 20, 21, 22, 23, 24, 25, 26, 27,
28 and 29 July 2021; 1,
9, 20, 25, 26, 27 and 28 August 2021. · Exceeded
emission limit of HCl on 27 and 31 July 2021. · Exceeded
emission limit of HF on 12 July 2021. |
In June, the exceedances
in emission parameters of CHP were found to be a result of the occasional low biogas
loading at the CHPs and unstable performance of CHP 3. The exceedances of
ASP were found to be result of incomplete combustion of biogas at ASP. In
July, exceedances in
emission parameters of CHP were found to be a result of the low biogas loading
at the CHPs. The exceedances of ASP were found to be result of unstable
condition at the column and the thermal oxidiser of
the ASP. In August, the exceedances in NOx of CHP were found to be
a result of the low biogas loading at the CHPs and the unstable condition of
CHP1. The exceedances of SO2 of CHPs and ASP were found to be
a result of the tripping of the desulphurisation system. The exceedances
of ASP were found to be result of unstable condition at the thermal destructor
of the ASP.
The Contractor has implemented
mitigation measures to control the exceedance including the maintenance and
fine-tuning of equipment of the ASP, the investigation on the underlying
reasons of exceedances in CHP and ASP and the continuous seeking of better and
more feedstock to increase biogas loading and testing at ASP to optimise
combustion efficiency and overall performance.
No non-compliance to the effluent
discharge limit was recorded during this reporting period.
The environmental control
/mitigation measures related to air quality, water quality, waste (including
land contamination prevention), hazard-to-life and landscape and visual
recommended in the approved EIA Report and the EM&A Manual were properly implemented
by the Contractor during the reporting period.
Monthly landscape and visual
monitoring were conducted in the reporting period. The necessary
landscape and visual mitigation measures recommended in the approved EIA Report
were generally implemented by the Contractor.
No complaint/summon/prosecution was
received.
|
|
|
|
([1])
As some of the minor items are yet to be closed out in March
2019, the construction phase EM&A programme and Operation Phase EM&A
programme were undertaking in parallel in March 2019.